May Release P0 Burndown — P0 Tracker

← prev  ·  Snapshot: 2026-05-09  ·  next →  ·  Target: May 21, 2026
Target Date
May 21, 2026
Open P0s
90
baseline
Closed
104
Total
194
Days Left
12
Burn Rate
~7.5/day
% Complete
54%

Burndown Chart

Open Issues by Stage

EnhancementTotalOpenClosed% DoneProgress
ENH-6726 Computer NxT 49 33 16 33%
ENH-6874 Computer Settings - Plans and Billing 25 16 9 36%
ENH-6023 Multiplayer Messaging with Agent 48 15 33 69%
ENH-5470 Automated Invoicing / Metronome Integration 14 9 5 36%
ENH-6613 [GA] Agent integration with Claude SDK 21 8 13 62%
ENH-6618 Computer Chat Experience 15 5 10 67%
ENH-6556 [GA] Human in the Loop, Confirmation Steps 3 2 1 33%
ENH-6878 Proactive Onboarding Skill 15 1 14 93%
ENH-6607 Computer Notifications and Sessions Discoverability 4 1 3 75%